Foster Creek Roundabout Update

Please see tentative schedule below:

  • An additional yield sign at the east side of the south bound lane of Foster Creek was installed yesterday afternoon and will remain in place until the raised median is installed.
  • Removal of electric message board is scheduled for 7-18
  • Install balance of inside curb on traffic circle – should be complete by 6-22
  • Install balance of outer curb on traffic circle – should be complete by 6-22
  • Pour truck aprons – should be complete by 6-25
  • Remove and replace fire station drive – complete by 6-29
  • Grading in the center circle – complete by 6-22
  • Grading behind the curb in the south and west quadrants – complete by 6-22
  • Installation of the concrete medians – should be complete by 6-26
  • Paving of Foster Creek, Williams Lane, and Song Sparrow – Paving to begin 6-25, We anticipate that either paving, striping, or some other work will be performed at night for the entire week 6-25 thru 6-29
  • Directional boring and ditching of lighting conduit – should be complete by 7-6
  • Thermo paint install and final signage– week of 7-16, most likely night work
  • Removal of remaining traffic control devices to occur once all signage and striping is complete.